Riyadh Metro

Non-shrink cementitious and epoxy grouts for joints between steel girders and precast deck units

Project type
Railways
Location
Riyadh, Saudi Arabia
Year
2016
Products
Flo-Grout 2, Flo-Grout EPCG

The challenge

The BACS consortium was responsible for the design and build of Lines 1 and 2 of the Riyadh Metro. These are part of a six-line network running 176 km across the city with 85 stations. In the deep underground stations, a traffic deck slab is built from steel girders and precast RC elements. The joints between them had to be filled with a material that can transfer and carry heavy dynamic loads. The grout had to give the flow needed on site, meet the specification and drawings, and stay within the budget for this work.

The DCP solution

DCP proposed a system of non-shrink grouts. Flo-Grout 2, a cementitious grout, was used where no dynamic load is expected. Flo-Grout EPCG, an epoxy grout, was used to fill gaps where heavy dynamic loads are expected. The filler content of Flo-Grout EPCG can be adjusted on site to get the right flow and a continuous fill.

DCP products used

Grouts and anchors Flo-Grout 2 General purpose non-shrink cementitious grout Product page: Flo-Grout 2Specifications: Flo-Grout 2
Grouts and anchors Flo-Grout EPCG High strength pourable epoxy foundation resin grout Product page: Flo-Grout EPCG

How it was applied

  1. Identify joints that carry heavy dynamic loads and those that do not.
  2. Fill joints with no dynamic load with Flo-Grout 2.
  3. Fill joints under heavy dynamic load with Flo-Grout EPCG, adjusting the filler content for flow and continuous fill.