Rookery South ERF

Metallic dry shake topping for wear-resistant floors under truck and loading shovel traffic

Project type
Renewables, Factories & Warehouses
Location
Stewartby, Bedfordshire, United Kingdom
Products
Tibmix
Rookery South Energy Recovery Facility, Stewartby (open the photo larger)
Rookery South Energy Recovery Facility, Stewartby

The challenge

The Rookery South Energy Recovery Facility (ERF) is built in a disused clay pit at Stewartby, Bedfordshire. It processes around 550,000 tonnes of non-recyclable waste a year and produces over 60 MW of electricity, enough for about 112,500 homes and businesses. The concrete floors needed a wear-resistant surface for constant truck and loading shovel traffic.

The DCP solution

DCP supplied TIBMIX, a non-oxidising, chemically inert, metallic dry shake topping for monolithic floors. It is a premixed blend of graded aggregates, additives and ordinary Portland cement. It gives a dense, tough surface that resists abrasion, wear, oil and grease, which suits heavy industry and power plants. The London-based contractor uses either Monoshake or TIBMIX from DCP when a dense surface and high wear resistance are needed.

DCP products used

Flooring Tibmix Pre-blended metallic dry shake floor topping Product page: Tibmix

How it was applied

  1. Place a well compacted, smoothed concrete slab and let the bleed water rise and evaporate.
  2. When light foot traffic leaves a 3 to 6 mm imprint, apply TIBMIX.
  3. On large areas, spread and trowel TIBMIX in one stage with mechanical spreaders.
  4. For manual work, spread two thirds of the TIBMIX first and let it absorb moisture until the colour is even.
  5. Float, spread the remaining third, then float for a final time.

The result

TIBMIX raised the surface wear capability of the new concrete by 300 to 500%, into a special wear class suited to heavy industry. The facility completed commissioning and was handed over to the operator within the agreed schedule, after less than three years of construction.

More photos

Mechanical spreader applying dry shake topping to fresh concrete (open the photo larger)
Mechanical spreader applying dry shake topping to fresh concrete
Power floating the slab after the dry shake application (open the photo larger)
Power floating the slab after the dry shake application